Abstract:
The aim of this study was to assess the determination of factors influencing
construction project performance in public institutions which was carried out at
Musoma and Butiama District Councils. The study comprises individuals from
Musoma District Council and Butiama District Council. The study was guided by
four objectives which are the effect of project planning on construction projects, the
effect of relationship management on construction projects, the effect of institutional
factors on construction projects in public institutions and the challenges affecting
construction project performance in Tanzania public institutions.
The study adopted explanatory research design were 114 respondents obtained
through random sampling and purposive sampling. Explanatory research design
employed to determine the relationships between variables. Data were collected
through questionnaire and documentary review to supplement the study, both
quantitative and qualitative approach was used. The collected data were analyzed
using factor analysis, linear regression analysis and correlation analysis. The study
found a significant relationship between project preparation, project schedule, trust,
communication, political interference, project supervision and technical competency
with project performance as all predicators were < 0.05. Furthermore, the study
revealed that lack of technical staffs, delay of project completion and inadequate
fund are the major challenges facing construction projects in public institutions.
The dissertation concluded that construction project performance in Tanzania public
institution is influenced by project planning, relationship management and
institutional factors, and revealed that 63% of the respondents agreed that lack of
technical staffs is the main challenges facing construction project in public
institution.
The study recommended that public institutions should ensure proper preparation of
projects; also project schedule should be prepared by skilled personnel in order to
ensure VfM in public construction projects. Also the government needs to ensure that
project funds are available before commencement of the projects. Additionally, the
government should make sure that the public institutions equipped with adequate,
skilled, competency and knowledgeable practitioners in order the public institutions
to achieve VfM in construction projects.